Resorce Graph
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
James,
quite the same in PWA; the chart is easily readable for few resources, and a nightmare if you have plenty
Cheers
Gentlemen,
You can show multiple resources on one graph!! By using the Analyse Timescale Data in Excel, you can export all the resource data from the Resource Usage or Resource Sheet view. In Excel, you can then convert the data to a Stacked Histogram or Stacked Column. This will give a different colour for each resource, for each time-period.
I did this some time ago. It worked beautifully - but it took a little time. The only real problem is if you have lots of different resource names. The colours then become diffcult to differentiate.
James
Thank You
unfortunately not; its only possible by using MS Project Server and Project Web Access