Resorce Graph

A
Alexandre Faulx-Briole 👤 Member for 23 years 5 months

James,

quite the same in PWA; the chart is easily readable for few resources, and a nightmare if you have plenty

Cheers

J
James Griffiths 👤 Member for 20 years 1 month

Gentlemen,



You can show multiple resources on one graph!! By using the Analyse Timescale Data in Excel, you can export all the resource data from the Resource Usage or Resource Sheet view. In Excel, you can then convert the data to a Stacked Histogram or Stacked Column. This will give a different colour for each resource, for each time-period.



I did this some time ago. It worked beautifully - but it took a little time. The only real problem is if you have lots of different resource names. The colours then become diffcult to differentiate.



James

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts