Changing Date ..Man Hours Change

Z
zulfi Ali 👤 Member for 21 years 7 months
Z
zulfi Ali 👤 Member for 21 years 7 months

Thank you very much Alexandre. Only one activity still showing the same attribute. Let’s see

Once more thanks a lot for your kind information.

A
Alexandre Faulx-Briole 👤 Member for 23 years 5 months

Ali,

Double-clic the task to open "Task Information", display "Advanced", change "Task Type" to "Fixed Work" to have the assignement rate changed instead of the amount of work.

Select together all the tasks you want and click the Task Information icon, then continue as above

Open Tools, Options, Schedule and change Task Type to Fixed Work to setup the tasks before you create it.

All the best

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts