Give Column Showing Original No. of Days Allocated

I
IT Student 👤 Member for 22 years 7 months
W
Will Russell 👤 Member for 23 years 2 months

If you have set a baseline then the information you want is in the Baseline Duration column. Just insert that column into the Tracking Gantt view.

You really should go on an introductory course!!



Will