Microsoft Project Member for 22 years 6 months Member for 22 years 7 months Submitted by Will Russell on Tue, 2003-10-14 08:00 Permalink RE: Give Column Showing Original No. of Days Alloc If you have set a baseline then the information you want is in the Baseline Duration column. Just insert that column into the Tracking Gantt view. You really should go on an introductory course!! Will Log in or register to post comments
Member for 22 years 6 months Member for 22 years 7 months Submitted by Will Russell on Tue, 2003-10-14 08:00 Permalink RE: Give Column Showing Original No. of Days Alloc If you have set a baseline then the information you want is in the Baseline Duration column. Just insert that column into the Tracking Gantt view. You really should go on an introductory course!! Will
Member for
22 years 6 monthsRE: Give Column Showing Original No. of Days Alloc
If you have set a baseline then the information you want is in the Baseline Duration column. Just insert that column into the Tracking Gantt view.
You really should go on an introductory course!!
Will