Task Progress Status Indicator?

Member for

22 years 6 months

The standard MSProject Gantt chart should show progress graphically, as a solid black line through the middle of the Gantt task bar.



If you want to show the progress graphically on a Summary bar then in the Bar Styles dialogue box insert a new bar with what ever symbol you want to use, in the “Show for……Tasks” column put in “Summary” then in the “From” and “To” columns put “Complete through”. This will show your symbol in the summary bar at the % complete of that summary bar.



Remember that MSProject puts these formats on in order, top to bottom in the Bar Styles box, so if you want the whole symbol to show put it below the style for the Summary Bar.



Will