Is it possible to split activity bars?

C
Chris Frank 👤 Member for 19 years 10 months
T
Tu Huynh Van 👤 Member for 19 years 10 months

David,



- I agree, we can "split" using suspend/resume but only for activities in progress, others we can not.



-Should using an activity specific calander,


K
Kym Lesinski 👤 Member for 19 years 10 months

David,



Your point is valid however there are always exceptions. Splitting activity bars would help me with KPI analysis, therefore becoming quite usefull on a number of my projects. What I’d say to Primaver is it’s always good to have options, make it possible and give us the choice to use it or not.



Kym.

D
David Kelly 👤 Member for 21 years 8 months

You can "split" using suspend/resume or an activity specific calander, but not under resource levelling.



Primavera has always resisted the temptation to allow multiple instances of the same activity number as in MSP. While this feature may help planning engineers, its a cost engineering nightmare. I am optimistic that Primavera will continue to resist imnplementing what I see as a mistake.

Forum Sponsor

Top Posters

Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts