MSP Retained logic or progress overide

F
Frank Neal 👤 Member for 23 years 4 months
A
Abdullah Merchant 👤 Member for 15 years 7 months

Hey Paul,

 

I just picked up your book.....99 tips and tricks with MS Project 2007. Thanks a lot for helping people like me in getting a jump start with MS Projet scheduling.

I am about to start planning a Project involving working on Gas piping and Utility area rebuilding. My project manager want us to maintain a Risk register, to be reffered to and discussed during our review meetings . I was wondering if you could guide me as to where i could find more information on this. I am familiar with the P6 Risk Register.....but i am relativeley new to MS Project.Is there any excell sheet available that may can be used efficiently, or any options available with MS Project 2007. Thanks again.

P
Paul Harris 👤 Member for 25 years 2 months

Not quite as simple as that, this is MSP.



Retained logic when:

1. Splitting Inprogress tasks is checked in Options and

2. The percentage complete is greater than 0% when there is an actual start.



Otherwise Progress override.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au

F
Frank Neal 👤 Member for 23 years 4 months

I have just run a test myself and it appears to be Retained Logic...unless someone else knows better!

Are there any adjustable settings in MSP?

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts