Oracle Primavera - PM6 Member for 21 years Member for 21 years Submitted by David Kelly on Wed, 2006-08-30 08:31 Permalink RE: How to show Progress on Baseline Bar shen, Primavera has no facility to do this. However you can use a global change create a pair of user defined dates which represent the liquidated part of the baseline bar, and use those dates to draw a bar which shows progress against the baseline. Log in or register to post comments
Member for 21 years Member for 21 years Submitted by David Kelly on Wed, 2006-08-30 08:31 Permalink RE: How to show Progress on Baseline Bar shen, Primavera has no facility to do this. However you can use a global change create a pair of user defined dates which represent the liquidated part of the baseline bar, and use those dates to draw a bar which shows progress against the baseline.
Member for
21 yearsRE: How to show Progress on Baseline Bar
shen,
Primavera has no facility to do this.
However you can use a global change create a pair of user defined dates which represent the liquidated part of the baseline bar, and use those dates to draw a bar which shows progress against the baseline.