Do you generally calculate time for prep activity as some sort of percentage time , utilised for actual actvity.
Today i was surprised tolearn that the activity of 10 hrs duration ,which i am tracking ,required an effort of 3 persons for full 12 hours yesterday so that activity can be started today .
I guess it is time for me to keep eye on preparatory activites , and resources required for the same.
Food for thought about prepartory activities . . . if there is a resource change of hands, even within the same company, consider breaking out the acitivity. Additionally, be guided by managable activity durations. Site activities greater than 30 calendar days should be split into increments not exceeding 30 calendar days to enable identification of slippage or production deviation in time to recover.
This is always something that we encounter when describing activities. When discussing with the engineers, they always fail to think of the "preparatory" activities. As a result the activities always take longer that shown on the project.
Yes, you could insert the prep. activities as an individual task, but it then becomes a monster to update. Personally, I try to ensure that the duration of the task takes account of the prep. activities. This is where the individual programmers style is employed - in knowing the full content of the activity as opposed to just its name.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi guys ,
Do you generally calculate time for prep activity as some sort of percentage time , utilised for actual actvity.
Today i was surprised tolearn that the activity of 10 hrs duration ,which i am tracking ,required an effort of 3 persons for full 12 hours yesterday so that activity can be started today .
I guess it is time for me to keep eye on preparatory activites , and resources required for the same.
Food for thought about prepartory activities . . . if there is a resource change of hands, even within the same company, consider breaking out the acitivity. Additionally, be guided by managable activity durations. Site activities greater than 30 calendar days should be split into increments not exceeding 30 calendar days to enable identification of slippage or production deviation in time to recover.
Hi,
In cases as descibed - I usually use the activty description as "Procure & Install" and have a duration that reflects the activity.
John
Hi Vinod,
This is always something that we encounter when describing activities. When discussing with the engineers, they always fail to think of the "preparatory" activities. As a result the activities always take longer that shown on the project.
Yes, you could insert the prep. activities as an individual task, but it then becomes a monster to update. Personally, I try to ensure that the duration of the task takes account of the prep. activities. This is where the individual programmers style is employed - in knowing the full content of the activity as opposed to just its name.
James.
for me this is not a problem.
task name is only a short description of a set of works.
e.g. "nozzle installation" make contains some hidden works, get the nozzle from warehouse, then goto jobsite....
any delay will cause "nozzle installtion" delay, so when update this task, show the delay thats all.
You do not need to think in such a detail way.
But some preparation works are very important, and should be consider as task. for example pipe fabrication,equipment procurement/delivery...
HTH