1. Prepare a Fragmentary Network (Fragnet) - A sequence of new activities and/or activity revisions, logic relationships and resource changes that you proposed to be added to the existing schedule to demonstrate the influence of impacts to the schedule. Your Fragnet shall identify the predecessors to the new activities and demonstrate the impacts to successor activities;
2. Insert the Fragnet into latest programm and Run the programme.
Your impact programme package may include the following:
From this we can come up with some process / method statement.
I did try (but i can do only during lean hours in my work) and we can share some notes.
then we will post in PP, for others to comment.
I would prefer Mr. Andrew will be our adviser
I have confidence in Mr. Andrew. So we will ask Mr. Andrew if he will be available as our adviser. By this post, hopefully Mr. Andrew will accomodate his precious time.
Sorry i dont have one , but just wanna tell u that the impacted as planned schedules reflect how the as-planned schedule theoretically could have been impacted as a result of various owner or contractor caused delays that are inserted into the schedule.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Ashraf,
Preparation of Impact Programme suggestion:
1. Prepare a Fragmentary Network (Fragnet) - A sequence of new activities and/or activity revisions, logic relationships and resource changes that you proposed to be added to the existing schedule to demonstrate the influence of impacts to the schedule. Your Fragnet shall identify the predecessors to the new activities and demonstrate the impacts to successor activities;
2. Insert the Fragnet into latest programm and Run the programme.
Your impact programme package may include the following:
1. Fragnet;
2. Impacted Programme;
3. Total Float Report;
4. Narrative Report;
5. Log Report.
Hope it helps...
Arman
Hi,Charleston-Joseph Orbe
Could you please send to us list of the summury points resulted from your discusion with Andrew.
Hello,
Please read the thread TIME IMPACT ANALYSIS
Focus on the post by Mr. Andrew
From this we can come up with some process / method statement.
I did try (but i can do only during lean hours in my work) and we can share some notes.
then we will post in PP, for others to comment.
I would prefer Mr. Andrew will be our adviser
I have confidence in Mr. Andrew. So we will ask Mr. Andrew if he will be available as our adviser. By this post, hopefully Mr. Andrew will accomodate his precious time.
Cheers,
charlie
Sorry i dont have one , but just wanna tell u that the impacted as planned schedules reflect how the as-planned schedule theoretically could have been impacted as a result of various owner or contractor caused delays that are inserted into the schedule.