Hi,
you can input these info. in Resource Usage View
insert a column overtime work
as for your example, put 11hrs in work, and 3hrs in overtime work
for your 2nd question, im afraid the first row cant be deleted.
hi ,
once i entered resource cost in Resource information dialog box , can someone tell me as why cant i delete that information once i have clicked OK.
OR please tell me how i can revise that information.