overtime calculations

Z
Zhang Haixiang 👤 Member for 21 years 2 months

Hi,



you can input these info. in ’Resource Usage View’

insert a column ’overtime work’



as for your example, put 11hrs in work, and 3hrs in overtime work



for your 2nd question, i’m afraid the first row can’t be deleted.

V
vinod raturi 👤 Member for 19 years 10 months

hi ,



once i entered resource cost in Resource information dialog box , can someone tell me as why cant i delete that information once i have clicked OK.



OR please tell me how i can revise that information.