now i got it . I put timing as 1:00 AM to 12:00 PM . 1:00 PM to 11:59 PM.
This time it worked .
now one more question , why my computer is not accepting time in format of eg 18:00 hrs or 20:00 hrs . it is automatically changing to 6:00 PM or 8:00 PM.
Thanks for the insight , that MSP is actually dealing for one day . Now i understand.
But isnt there some other way , to club those timing in one calander so as to reflect actualy way that our plant is working.
I tried putting 1:00 AM to 6:00 AM , 6:00 AM to 12:00PM , 1:00 PM to 6:00 PM , 6:00 PM to 12:00 AM . But still it didnt work . i guess i will have to split into two as you suggested.
in this dialog box, the time is only for one day (0:00 to 24:00).
the time you input spans two days (e.g. day 16AUG is selected but the time you input start 16AUG 6:00 am end 17AUG 6:00am)
How can MSP deal with it.
it seems that you are using only one calendar (standard) for this two shifts. It does not make sense, because you can not assign that some activities is night shift, others day shift.
these is no difference to one shift 22hours/day.
I suggest you creat two calendars one for day shift, one for night shift. and input time as mentioned in my previous post
In change working time Dialog Box For Standard (project calander) If i put my input as 6:00AM to 12:00PM , 1:00 PM to 6:00 PM , 6:00 PM to 12:00AM , 1:00 AM to 6:00 AM.
I am getting message as "start of shift must be later than end of previous shift"
AS per above timing our plant works , why am i unable to change as per above format.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Thanks Zhang ,
it worked.
Hi,
For the time format,its controled by windows.
try control panel-> date and time to change the setting
Hi zhang ,
now i got it . I put timing as 1:00 AM to 12:00 PM . 1:00 PM to 11:59 PM.
This time it worked .
now one more question , why my computer is not accepting time in format of eg 18:00 hrs or 20:00 hrs . it is automatically changing to 6:00 PM or 8:00 PM.
Any suggestion on that , as to how to change it ?
Hi Zhang ,
Thanks for the insight , that MSP is actually dealing for one day . Now i understand.
But isnt there some other way , to club those timing in one calander so as to reflect actualy way that our plant is working.
I tried putting 1:00 AM to 6:00 AM , 6:00 AM to 12:00PM , 1:00 PM to 6:00 PM , 6:00 PM to 12:00 AM . But still it didnt work . i guess i will have to split into two as you suggested.
thanks,
Hi,
in this dialog box, the time is only for one day (0:00 to 24:00).
the time you input spans two days (e.g. day 16AUG is selected but the time you input start 16AUG 6:00 am end 17AUG 6:00am)
How can MSP deal with it.
it seems that you are using only one calendar (standard) for this two shifts. It does not make sense, because you can not assign that some activities is night shift, others day shift.
these is no difference to one shift 22hours/day.
I suggest you creat two calendars one for day shift, one for night shift. and input time as mentioned in my previous post
Hi ,
In change working time Dialog Box For Standard (project calander) If i put my input as 6:00AM to 12:00PM , 1:00 PM to 6:00 PM , 6:00 PM to 12:00AM , 1:00 AM to 6:00 AM.
I am getting message as "start of shift must be later than end of previous shift"
AS per above timing our plant works , why am i unable to change as per above format.
Hi,
day shift :
from 6:00 to 12:00
13:00 to 18:00
night shift:
from 1:00 to 6:00
18:00 to 0:00
suppose you are using one calendar for day shift and another for night shift
in the option-> calendar, change hours per day to 11