Hello,

in "change working time" dialog box,select all the days,you want to change, then type in the time in "from" "to" area.(start from 0:00 ), this will change the working time for the selected days. and the day will be shaded to show that the working time was changed, see left "legend "

there’s a standard "night shift" calender in MSP,check it to see how it works.



to select all the days, click and drag the week title.



HTH