Nigel Winkley 👤 Member for 20 years

Santosh



I did a quick fix a while ago.



I did as your PM requested and added a bar for the delay. This was then linked to the other activities retaiining the original logic as well. All activities were then ’delayed’ by the new bar and when the delay was complete they re-started.



Yes, I know it is messy and probably not ’good practice’ but it took ten minutes and got me out of a hole!



Cheers



Nige