P5-Top Down Estimation!
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Suraj,
Yes. You will need to set the estimation factor to the original duration. This is possible using global change, however it would be simpler if the global change that does this selects only activities at level 4 of the WBS - that way the TDE run can include the whole project, as activites not at level 4 will have an estimation factor of 0.
There is no way I know of automatically selecting "level 4" activities, perhaps an activity code could do this?