Thanks for responce. Actually i mistakingly got an idea that these data value can be shown in Res/Cost Profile which one can print under the gantt chart.
Regards
Rashid
Hi, I think at Resource/Cost Graphics Report, just check Display Data Values.
Suraj,
You wrote that the values could be shown/printed over the histograms in P3. Could you please let me know as to how it can be done.
Thanks.
Regards
Rashid
Yes ... i said "sometimes"
Regards.
Well..It has its drawback but has good merits too..
Like yesterday I was asked to make a small programm in 30 min for presentation.It was possible to complete it in allocated time because of the ease of adding ,shifting,copy-pasting WBS In P5.It was not possible on P3.
Cheers
Suraj
one more "walk back" on P3e / P5 versions ... sometimes i miss P3 ...
u cant, u have to dbl. click on every bar in the graphical report to show its value.
Or u can go for a tabular report and export it to excel and make a manual histogram which show values on the top of the bars !!!