Primavera -Resource constrained schedule

R
Renju M 👤 Member for 21 years
D
Dayanidhi Dhandapany 👤 Member for 23 years 2 months

primavera can’t identify the excess qty on its own, but you can assign the 2.5km to a custom data items(user defined variable) and try to summarize the BQ of the 3 related activities and then you can find variation between the two using global change or by anyother simple method.



by the bye? where is the attached file? you can’t attach anything to this forum?. if you want to get clarify anything send the file to [email protected] and inform me via private message about the file.