Primavera -Resource constrained schedule
Forum Sponsor
Top Posters
Jaturapit Multongka
1 posts
James Williams
74 posts
Haque Nawaz
10 posts
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
primavera cant identify the excess qty on its own, but you can assign the 2.5km to a custom data items(user defined variable) and try to summarize the BQ of the 3 related activities and then you can find variation between the two using global change or by anyother simple method.
by the bye? where is the attached file? you cant attach anything to this forum?. if you want to get clarify anything send the file to [email protected] and inform me via private message about the file.