Reamaining Early Start!!!

N
Nigel Winkley 👤 Member for 20 years

A quick answer...



This often happens when the predecessors have not finished in FS relationships.



If activity A is FS with activity B and B has started without A finishing then B will have a ’gap’. (The logic is saying that activity B cannot continue until A finishes in effect.) This happens when the scheduling is set to retained logic. If you change it progress override then you should not see any gap.



Hope this helps.



Cheers



Nige

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts