Productivity rate = [Work quantity/{activity duration * resource usage}]
Productivity may be measured as the quantity of work per one hour, or as quantity of work hourd per one unit of work quantity.
Best Regards,
Vladimir
Can any one tell the specific formula for calculating productivity.
Frans,
if you want to use productivities in schedule development try Spider Project (Demo can be downloaded from http://www.spiderproject.ru/spider_e.php).
In this package you can assign productivities manually or create Productivity database and use it in all projects of the organization.
I dont know why work quantities and resource productivities are not supported by other software packages.
Regards,
Vladimir