if one of the pred. of the milestone have a min. free float,that not means this pred. is driving the milestone, because its succ other than this milestone may cause the min FF. Am i right?
It is possible for MS Project to provide an analysis of the activity driver information. This needs a bit of additional VB coding, but will quickly and clearly show the full CP\Driver for each selected milestone.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Tom,
Good method, but it is not so accurate.
if one of the pred. of the milestone have a min. free float,that not means this pred. is driving the milestone, because its succ other than this milestone may cause the min FF. Am i right?
Hi all
I have the same issue in MSP, this is how I have addressed it (partly):-
Lets say you have 20 or so activites feeding into a milestone and you want to identify which ones are driving
First filter on tasks which have the milestone as a succesor, then filter these for criticality or free float.
My understandin gof the definition if driving is :-
Those activities preceeding an activty which are either critical or have minimum or zero "free float"
i.e. any delay to these preceeding activities will inturn delay the current activity
I would be pleased to get some feedback an dview on this solution
Kind regards
Tom
Im writing a VB code but have some problem
the code can only deal with Lag in day or eday,for lag as 50% the result is no correct.
the method is to caculate the start date for the task using each pred. if the caculated date is the same as MSP, then the Pred. is considered driving.
Is there any other easy method?
Dear All,
It is possible for MS Project to provide an analysis of the activity driver information. This needs a bit of additional VB coding, but will quickly and clearly show the full CP\Driver for each selected milestone.
Regards
Robyn
Hello,
MS Project up to 2003 and Server ignores what a driving / non driving predecessor is.
To get what you want, you could set Tools, Options, Calculation, Tasks are critical ... to more than 0, and so on.
Or build a filter whereto enter the desired value of slack.
Alexandre Faulx-Briole