I Think Fractions Are Very Important When The Project Duration Is Small- Lets Say For One Week Project
Hemanth,
If you enter a decimal value in the %Complete field, MS Project rounds the value to the closer integer:
50.25 = 50, 50.75 = 51
MS P understands 2 decimal figures
Alexandre
Dont think so.
Sorry for my last night posting about this subject(It seems that i was too tired)
Yes its straight forward . Just activate the Tracking toolbar, which includes susch macros