1. If the resource for the task is work ( not material) and the task has only one resource ( or has several resource, but you do not want to know the value for each resource) then you can try analyze timescaled date in excel Its on the analysis tool bar. if you can not see it, right click on the tool bar,then check it.
Follow the instruction, then you will get a excel sheet. you can have planned work for every day(or week, month...) for each task.
2.if your resource is material or you have more than 1 resource for each task and want to have the value for each resource.
change to task usageview, then use copy & paste to transfer all the data to excel, you will get a sheet with planned work for each resource and task
Ok, My problem is: For a particular Task - I want to know the Percentage of Works Planned in a particular month, I have the Quantity for the Task and the Rate, from which I will get the Amount.
So Getting the percentage of works planned for the required month will give me the exact Budgeted Amount for the particular month.
So can I use Filters to get the percentage of works planned for the required month and get the correct Budgeted Amount or is there a better way?
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Thank you sir,
Seems my work wont cut out so easily,
Will have to take the longer route
Cheers
Jatin
Its not so easy to do this.
1. If the resource for the task is work ( not material) and the task has only one resource ( or has several resource, but you do not want to know the value for each resource) then you can try analyze timescaled date in excel Its on the analysis tool bar. if you can not see it, right click on the tool bar,then check it.
Follow the instruction, then you will get a excel sheet. you can have planned work for every day(or week, month...) for each task.
2.if your resource is material or you have more than 1 resource for each task and want to have the value for each resource.
change to task usageview, then use copy & paste to transfer all the data to excel, you will get a sheet with planned work for each resource and task
hope this helps
hi
Ok, My problem is: For a particular Task - I want to know the Percentage of Works Planned in a particular month, I have the Quantity for the Task and the Rate, from which I will get the Amount.
So Getting the percentage of works planned for the required month will give me the exact Budgeted Amount for the particular month.
So can I use Filters to get the percentage of works planned for the required month and get the correct Budgeted Amount or is there a better way?
Cheers
Jatin
I mean you can not show part of a task.
You can scroll the timesacle,so you can alway see the end of the task, even the task last for years.
A filter only picks up those tasks meet certain Criteria then show them on the screen.
there are only two option show or not show.
Once the task is shown on screen, then you can access all information of this task e.g. finish date, % complete, resource, cost...
theres nothing to do with % planned work.(no such a field in MSP)
So for your example, you want to show the activity or not?