Do not ask for too many information for the report.
Think about what information really needed.
Sometimes, contractors can not follow , and you will get nothing.
for daily:
1) manpower for every trade, carpenets, steel fixers, etc..
2) specific activities for today, activities for tomorrow, and activites for yesterday
3) No, of labours for every activity, and location of the activity.
4) equipments
for weekly,
1) Manpower histograme
2) Updated programme (schedule)
3) no. of completed activity during this week, previous week, and total todate,
4) planned Vs actual of every major/semi-major activity as needed
5) planned Vs actual of progress and cost, for every week and cumulative
6)submittals status
7) etc.., there are lot and lot of things can monitor, just start with what u knwo now, and you can enhance it further
hope thats help despite it is not a fully complete list.