Report Formats

Z
Zhang Haixiang 👤 Member for 21 years 2 months

Do not ask for too many information for the report.

Think about what information really needed.

Sometimes, contractors can not follow , and you will get nothing.

W
W A 👤 Member for 20 years 1 month

for daily:

1) manpower for every trade, carpenets, steel fixers, etc..

2) specific activities for today, activities for tomorrow, and activites for yesterday

3) No, of labours for every activity, and location of the activity.

4) equipments



for weekly,



1) Manpower histograme

2) Updated programme (schedule)

3) no. of completed activity during this week, previous week, and total todate,

4) planned Vs actual of every major/semi-major activity as needed

5) planned Vs actual of progress and cost, for every week and cumulative



6)submittals status



7) etc.., there are lot and lot of things can monitor, just start with what u knwo now, and you can enhance it further



hope that’s help despite it is not a fully complete list.




Forum Sponsor

Top Posters

Erim INANC
2 posts
gorilpk
0 posts
Ricky
0 posts
pinoyplanner
1 posts
Siddharth Ranadive
1 posts
Aidar Kurmantayev
0 posts
Dave Morgan
0 posts
blake333_
0 posts
Mohammed Netarwala
12 posts
Moahmed
0 posts