It's how MS Project calculates Duration and Work in formulas. You basically have to convert it into minutes, so 1 day would equal 8 hours (if you use 8 hrs as a standard day), and as there are 60 minutes in each hour you end up with a value of 480.
Yes youre right Ioannis. There is an overall progress information in the Statistic based on duration too. But I need progress variance per activities based on duration.
Thanks alot Harris, its good idea. I will assign budget by using formula : Duration X Unit Price. Unit Price is $1. Then Ill get BCWS and BCWP in $. For the percent BCWS or BCWP just dividing them with the Budgetted Cost of each task then the delta of both percentage is the % variance.
1. Enter a dummy cost for the software for each activity which will calculate the BCWS. This could be using the Fixed Cost column. Then use a Custom column to calculate the Planned % Complete. The cost could be the same as the original duration if you are looking for Planned % Complete based on Duration, or you could enter some more realistic values.
2. Use a Custom Column to calculate the % Complete based on the Early Start, Early Finish and Status Date.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
Thanks Harris for your response. You are right that progress variance is calculated based on duration if there is no costs assigned. Im sure MsP plot their zig zag progress line using this method. But my problem is still same how to show such percent variance if the progress calculated based on duration.
Unless there is a value in terms of cost, hours or deliverables etc assigned to activities and progress of these is measured then it is not possible to give a percentage variance except as a function of the durations of activities.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Rohit,
It's how MS Project calculates Duration and Work in formulas. You basically have to convert it into minutes, so 1 day would equal 8 hours (if you use 8 hrs as a standard day), and as there are 60 minutes in each hour you end up with a value of 480.
Regards,
Darren Kosa
Ioannis,
The numerical 480 in your formula, what does it denote?
Rohit
Plsease try the formulas as shown below; may be what you would expect
Nunber 1
(Days of workload should have completed as per status date, measured on Baseline data
Nunber 1
IIf([% Complete]>0;IIf([% Complete]<100;([Baseline Duration])/480-((ProjDateDiff([Status Date];[Baseline Finish];"standard"))/480);0);0)
Number 5 (Per Task % delay) (only for active tasks)
IIf([Number1]<>0;(([Number1]/[Baseline Duration])*480*100)-[% Complete];0)
Yes youre right Ioannis. There is an overall progress information in the Statistic based on duration too. But I need progress variance per activities based on duration.
Regards,
RH
If I have understand correctly your question, you can have percent completion value on project duration provide you have already enter actual data,
For an overall view, go to Project>Project Information Statistics
Thanks alot Harris, its good idea. I will assign budget by using formula : Duration X Unit Price. Unit Price is $1. Then Ill get BCWS and BCWP in $. For the percent BCWS or BCWP just dividing them with the Budgetted Cost of each task then the delta of both percentage is the % variance.
Thank you very much.
Kind Regards,
RH
You could try a couple of options
1. Enter a dummy cost for the software for each activity which will calculate the BCWS. This could be using the Fixed Cost column. Then use a Custom column to calculate the Planned % Complete. The cost could be the same as the original duration if you are looking for Planned % Complete based on Duration, or you could enter some more realistic values.
2. Use a Custom Column to calculate the % Complete based on the Early Start, Early Finish and Status Date.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Thanks Harris for your response. You are right that progress variance is calculated based on duration if there is no costs assigned. Im sure MsP plot their zig zag progress line using this method. But my problem is still same how to show such percent variance if the progress calculated based on duration.
Thanks in advance.
regards
Unless there is a value in terms of cost, hours or deliverables etc assigned to activities and progress of these is measured then it is not possible to give a percentage variance except as a function of the durations of activities.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting