Lag’s Calendar

P
Paul Harris 👤 Member for 25 years 1 month

There are two other options for lags:



Elapsed lags, say FS+10edays will give you an elapsed lag ignoring the Successor calendar.



Percent Lags, say FS-50% which will allow the successor to start 50% through the duration of the predecessor.



P3 and SuerTrak use the predecessor calendar but Primavera Enterprise gives several options.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au

T
Tom Boyle 👤 Member for 19 years 6 months

In MSP 2003, working days in lag relationships are computed based on the Successor Activity’s calender. This defaults to the Project Calendar if no other calendar is specified for the successor activity. (I think P3 uses the Predessesor’s calendar).



[This is a correction I just learned today, so I thought I’d post it for the record.]

BR, tom

I
Ioannis Leontiou 👤 Member for 20 years

It uses Default Calendar, Unless yuo had configured and assign a Task Calendar for the tasks reference to

M
Marcio Sampaio 👤 Member for 20 years 7 months

Thanks Ronald.



I’m not a MSP user ... so i dont use to read MSP threads ... thats why i didn’t know about that.



Thanks again.



Regards.



Marcio Eduardo

R
Ronald Winter 👤 Member for 23 years 5 months

I have been told that MS Project lags are calculated using the Default Calendar.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts