Equipment in MS Project

A
Andrew Levitt 👤 Member for 20 years 2 months

Sounds like no then. It’s not isolation that I’m after, but accurate worker-hour calculation together with load levelling and over-allocation notification. thanks for the reply.



andrew

P
Paul Harris 👤 Member for 25 years 2 months

Andrew



Your options are Work or Material.



You can tag resources, say with a Group, to isolate if it is equipment or people, this may assist.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au