Sounds like no then. Its not isolation that Im after, but accurate worker-hour calculation together with load levelling and over-allocation notification. thanks for the reply.
andrew
Andrew
Your options are Work or Material.
You can tag resources, say with a Group, to isolate if it is equipment or people, this may assist.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au