Calculating Planned manhours for an Project

V
Vladimir Liberzon 👤 Member for 25 years 5 months

Ram,

Spider Project uses other approach to calculating manhours.

You can create databases (reference books) with the productivity norms for different types of resources on different types of work. Assigning types to resources and activities in your schedule and entering quantities (volumes) of work to be done on each activity you will be able to calculate project resource (cost, supplies) constrained schedule that is based on your norms and project restrictions (resource availability, financing schedule, supplies schedule). The software will calculate activity durations and planned manhours (and machine hours too) basing on your norms and will supply you with any kind of reports in table or graphic forms. Total manhours, trade manhours, manhours for any group of trades, etc. by hours, days, weeks, months, quarters, years and user defined periods (cumulative or not).

Regards,

Vladimir

M
Marcio Sampaio 👤 Member for 20 years 8 months

If u have Mh on your schedule - like a resource - P3 will give u an S-curve.



Regards.

C
Charleston-Joseph Orbe 👤 Member for 21 years

Hi Ram,



Planning Planet got productivity rates.



You may take a look at those productivity rates. It maybe of help to you, otherwise you can always revert to PP forum.



Cheers,



Charlie

Forum Sponsor

Top Posters

James Williams
74 posts
Erim INANC
2 posts
gorilpk
0 posts
Ricky
0 posts
pinoyplanner
1 posts
Siddharth Ranadive
1 posts
Aidar Kurmantayev
0 posts
Dave Morgan
0 posts
blake333_
0 posts
Mohammed Netarwala
12 posts