CONTRACT PROGRAM-INCORPORATION OF COMMENTS

K
Kumar I 👤 Member for 22 years 11 months
K
Kumar I 👤 Member for 22 years 11 months

Clive,

Program has to be approved by the clients representative.Its now few months since the initial baseline was submitted,since then the baseline

program has been resubmitted a couple of times to incorporate the clients comments and to comply with the contract specs.



The delays are of our ( contractors) making.Delays have occured recently,and in our proposed resubmission of the program,we intend to increase the durations of the foundations to cover our delay.My question is can the client object to the above.



Are you saying from the date our initial baseline has been submitted the baseline should not be revised,(to absorb the delays occuring after the initial baseline submission date) in the subsequent baseline resubmittals for approval.

Forum Sponsor

Top Posters

James Williams
74 posts
Erim INANC
2 posts
gorilpk
0 posts
Ricky
0 posts
pinoyplanner
1 posts
Siddharth Ranadive
1 posts
Aidar Kurmantayev
0 posts
Dave Morgan
0 posts
blake333_
0 posts
Mohammed Netarwala
12 posts