Strategic reporting using EV

S
Simon Springate 👤 Member for 20 years 7 months

Thanks Joao

Do you have a more specfic ref for the Ghent paper, general searching on their site is not getting me far



Reguardless your reply is much appreciated

J
Joao Ribeiro 👤 Member for 23 years 3 months

Have you considered using the ones proposed by Lipke, or similar (SPI(t), SV(t),IEAC(t),...)?



There is an academic paper at Ghent’s University site.



Cheers.

S
Steven Oliver 👤 Member for 23 years 8 months

Something like:-



No of milestones achieved vs planned ?

Achieved % Complete vs Planned ?



etc





If you are comparing projects across a portfolio, then pick on the things that are common between them .



Actually, (IMHO) this is one of the more useful ways CPI (or SPI) can be used.

Forum Sponsor

Top Posters

James Williams
74 posts
Erim INANC
2 posts
gorilpk
0 posts
Ricky
0 posts
pinoyplanner
1 posts
Siddharth Ranadive
1 posts
Aidar Kurmantayev
0 posts
Dave Morgan
0 posts
blake333_
0 posts
Mohammed Netarwala
12 posts