Resource progress (v.5.0).

M
Marcio Sampaio 👤 Member for 20 years 7 months

Rajeev,



The option is select. But resources are still not automatically progressing.



I’m afraid it’s something new on V.5 (or a bug). Better return to P3e v.4.1



Regards.



Marcio Eduardo.

R
Rajeev Nelliyodan 👤 Member for 24 years 3 months

Try clicking on "Recalculate Actual Units and Cost when duration % complete changes" under calculation tab in Project view.