How to create resource histogram
Forum Sponsor
Top Posters
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
Go to:
Tools / Graphic Reports / Resource & cost.
I suggest you Add a new report and work through each of the selection tabs for setting up the report.
Resource Selection, Content, Date and Selection are the ones you should focus on first.
In Resource Selection you need to select the resource you would like to create the histogram for.
Content selects between curve & Histogram and allows you to include targets.
Date allows you to select your timescale and time intervals.
Selection allows you to make a selection of what you would like to create the histogram for.
I have of course assumed that you have resource loaded your schedule. If not you need to create resources and allocate them to your activities prior to doing any of this.
I suggest you set this up and see if you could get it to work, if not, let us know what you have problems with.
Regards
Jackie