V5 : Resource Distribution

A
Amar Aghana 👤 Member for 20 years 10 months
M
Mohammed Abo El Magd 👤 Member for 21 years 6 months

The best way to distribute multiple effort on one activity is to make your activity type (Resource dependant) and create a special calendar to this resource. Then assign the calendar to the resource. Then assign him to the activity with the total units. By the way there is no way to get 2 figures after decimal but Edit _ User preferences.

A
Amar Aghana 👤 Member for 20 years 10 months

One more challenge:



I have activity duration in "Days"



and



Estimated Resource Units in "Manhours"



I converted the manhours to Mandays.



Is there any way to have decimals for Mandays for resource units I mean 1.5mandays, 0.5 Mandays, 2.75Mandays etc.

D
David Forrest 👤 Member for 24 years 6 months

Check project options, it has a check box for allowing or dis-allowing this feature.



Open your project



Go to Enterprise



select Projects



Select Resources, the tab is on the top left hand side.





Regards





Dave

B
Brent Hursey 👤 Member for 20 years 7 months

Is this suppose to work in any version of P3E? I can not add multiple occurrences of the same resource.



Thanks,

Brent

D
David Forrest 👤 Member for 24 years 6 months

The best solution for distributing variable effort on an activity is to multiple assign the resource, select a start and finish date for the resource and assign the number of days for the period.



e.g.

Resource 1 starts 1st jan finishes end jan 20 man days

resource i starts 1st feb finishes end Feb 15 man days



etc etc

It works OK for me



You can add the start and finish dates to the resource window, right click on one of the title fields at the top and select start and finish fields.


S
Steven Oliver 👤 Member for 23 years 7 months

As I said, Resource Curves are associated with resources, not activities

A
Amar Aghana 👤 Member for 20 years 10 months

Thanks Steven.



using the same resource multiple times: This I am aware and using for projects. But I thinking how to load as I explained earlier. I have created a user defined curve and almost matched the distribution required.



"Curve" is available for global change field



"Curve" is not availble in activity column. Do you have any idea?

S
Steven Oliver 👤 Member for 23 years 7 months

________________________________________________________

Sorry Steven, With that I will not know what is my total resource requirement for a particular resource.

________________________________________________________



Perhaps, you have misunderstood. You can use the same resource multiple times on an activity. Specify the duration and the lag (lead) from the start of an activity.



_______________________________________________________

Steven, I could copy an exitsting res curve and modify according to the requirement.



Do you know, how to add resource curve to activity column? or how to use resource curve field in global change to assign resorce curve in faster way./

_________________________________________________________



Unless your activity exactly equates to that which you can generate using a resource curve then you will not achieve your desired result.

Resource curves are associated with resources, not activities.

A
Amar Aghana 👤 Member for 20 years 10 months

Steven, I could copy an exitsting res curve and modify according to the requirement.



Do you know, how to add resource curve to activity column? or how to use resource curve field in global change to assign resorce curve in faster way./

A
Amar Aghana 👤 Member for 20 years 10 months

Sorry Steven, With that I will not know what is my total resource requirement for a particular resource.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts