Critical Chain Vs C.P.M
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
I attended a seminar on this (actually they were talking about the Protocol), when one of the speakers talked about what he promised was a better way of scheduling by using C.C.
I did a quick survey among fellow participants at the end of the seminar, most of them felt that the speaker was waffly and copied his notes from books.
Guys, dont waste your money on these seminar nonsense in future.
Paul Cunningham, Hong Kong/Singapore
The last time I read up on the Critical Chain method, the papers were riddled with jargon such as “evaporating clouds”, “self-reinforcing negative feedback loops”, “bad multitasking”, “leverage points” and “buffers”. What I got out of it after distilling it into laymans terms was the following (if I am wrong, somebody please correct me):
commit to the true (lean estimate) critical path. The fat will shrink as the schedule slips.
Of the above, the only items that are specific to Critical Chain is the addition of the "buffer management", which to my mind is the same thing as float management in CPM except for the fact that you actually may build some fat in your critical path schedule.
Personally, I prefer to schedule without fat and manage the project to the most aggressive objective. It would seem to me that building fat into your schedule is just setting yourself up for Parkinsons Law, "Work expands to fill the time available."
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software
What I ment was, PMI seems to silent on this issue, or I have yet to read about PMIs stand on this issue, but if you go through PMI database about CC there is a lot of write up in PM Journal, Network and other papers presented at PMI fourm quoting the CC is better management system compared to CPM.
Check it out
[quote]PMI U.S have acknowledge Critical Chain as a better system than CPM[/quote]
Do you have a reference to support this?
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software