This is a common misconception. You can’t create an independent schedule and then assign it as a baseline to another schedule. Even through the two schedules look identical on the outside to you, Primavera clearly sees them as different on the inside and has nothing to match up. The Activity IDs that you see are not the ones that Primavera actually uses to identify the activities.
The only way to make a baseline schedule is to create it using the Make Baseline feature. Good luck!
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Jorge,
This is a common misconception. You can’t create an independent schedule and then assign it as a baseline to another schedule. Even through the two schedules look identical on the outside to you, Primavera clearly sees them as different on the inside and has nothing to match up. The Activity IDs that you see are not the ones that Primavera actually uses to identify the activities.
The only way to make a baseline schedule is to create it using the Make Baseline feature. Good luck!
Are the activity IDs the same? Did you put a check on the Primary baseline under the Project, Baselines window?
Best,
Jorge
Learning:
I have created a new baseline before updating the current project. Then it worked. Is this correct or while doing trial and error, something happend?
Christian, I do not know what is patched. However, I have tried all options in View>Bar>Bar chart Options.
This is not the problem with Bar Formats. Because, when I tried to make the current as baseline, the dates and bar are appearing.
But when I try to attach other project as baseline to current, the dates/bar disappearing.
Amar
Does your v 4.1 have a patched? try to check bar formats...
Regards,
Christian
Any ideas pls