PROGRAMMING AND EXECUTION BY VARIOUS PACKAGES

K
Kumar I 👤 Member for 22 years 10 months
K
Kumar I 👤 Member for 22 years 10 months

There is a master plan,there is a program when the various package contractors will be on board at which time the detailed program of the respective package will be available,the issue is till that time how the program of the contractors already on board can be dealt with,since they need to be co-ordinated with other packages who will be mobilised at a latter stage of the project.

O
Oscar Wilde 👤 Member for 20 years 8 months

Kumar

are you saying there is no project plan

the client does not have one

the PM does not have one

how are you deciding when to go to tender

what are you supplying in the package tender documentation

sounds like a recipe for disaster

I am intrigued

S
Sen Moc 👤 Member for 20 years 9 months

Kumar,



The Owners and the Project Management are the one deciding the programming & execution of the project based on their best interest.



Are you on the contractor side? If you’re not happy with your present situation, better to transfer to the Owner’s Project Mgt Team.



Cheers!

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts