It all depends on what one is planning and the degree of understanding the job being planned. I have worked on plans where everybody was quite clear what needed to done and the interdependencies between each player. One can easily generate a robust logically driven network with time and resource in less than a month.
On the other hand I have worked on large systems engineering projects where one of the key roles of the planner was to drive out engineering process (in conjunction with the Chief Engineers) in addition to duration and resource. In such cases the engineering process to be followed defines the planning dependencies. Naturally this type of project takes much longer to reach a satisfactory programme that all players buy in to. It has taken me around 5 to 8 weeks to have a rough programme that all buy into and then another couple of months to polish. Activity size was around 1,300 to 2,000 activites with an appropriate amount of dependencies.
Are you going to type one by one of the 2000 activities?
Are you going to input dependencies one by one activity?
Do you have an orderly procedure that takes you through the whole scope that helps you define the division of stretches, project elements and activity operations (actions)to in turn define activities? And whether you are going to define activities that will eencompass one trade or crew, or will they encompass more than one?
In summary, do you have a defined set of proven procedures, guidelines and criteria the take you through the process of designing schedules?
Project nature is big factor that defines schedule development duration. But, I would say that schedule development nature is a bigger one. Especially when we are talking about thousands of activities.
In other words, how long does it take to go from Cancun, Mexico to Paris, France?
That depends in large part upon the type of schedule being defined and the caliber of the resources the planner has to draw upon. Scheduling work that is repetitive in nature (such as equipment maintenance or construction) where the scope has a large overlap with historical projects should be fairly quick to produce.
Projects that encompass something entirely new (list software development, design, etc.) would require more effort in defining the tasks. Im not sure that a metric for scope development is applicable when the project is completely unknown (has to be defined from scratch).
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
It all depends on what one is planning and the degree of understanding the job being planned. I have worked on plans where everybody was quite clear what needed to done and the interdependencies between each player. One can easily generate a robust logically driven network with time and resource in less than a month.
On the other hand I have worked on large systems engineering projects where one of the key roles of the planner was to drive out engineering process (in conjunction with the Chief Engineers) in addition to duration and resource. In such cases the engineering process to be followed defines the planning dependencies. Naturally this type of project takes much longer to reach a satisfactory programme that all players buy in to. It has taken me around 5 to 8 weeks to have a rough programme that all buy into and then another couple of months to polish. Activity size was around 1,300 to 2,000 activites with an appropriate amount of dependencies.
Hope this helps
Bryce:
Are you going to type one by one of the 2000 activities?
Are you going to input dependencies one by one activity?
Do you have an orderly procedure that takes you through the whole scope that helps you define the division of stretches, project elements and activity operations (actions)to in turn define activities? And whether you are going to define activities that will eencompass one trade or crew, or will they encompass more than one?
In summary, do you have a defined set of proven procedures, guidelines and criteria the take you through the process of designing schedules?
Project nature is big factor that defines schedule development duration. But, I would say that schedule development nature is a bigger one. Especially when we are talking about thousands of activities.
In other words, how long does it take to go from Cancun, Mexico to Paris, France?
Tomas Rivera
That depends in large part upon the type of schedule being defined and the caliber of the resources the planner has to draw upon. Scheduling work that is repetitive in nature (such as equipment maintenance or construction) where the scope has a large overlap with historical projects should be fairly quick to produce.
Projects that encompass something entirely new (list software development, design, etc.) would require more effort in defining the tasks. Im not sure that a metric for scope development is applicable when the project is completely unknown (has to be defined from scratch).
Bernard Ertl