% of Progress for total project

E
Edgar Ariete 👤 Member for 20 years 10 months



How are you Rolyn?



Sorry, I didn’t mean it. I’m just trying to add some spice.

It’s fun to read the posts of the radical Planners in here.



I’m not as big as you are. i’m just a chick coming from the rain, hungry & wet, & trying to get some intellegent informations from the big boys.. and thinking that this is open...i’m just trying to be me.



Thanks Rolyn, Raja & Alex



By the way, my answer for the Subject is 100% if the project is completed.



thanks

A
Alex Wong 👤 Member for 23 years 3 months

Raja



I fully understand the reason of why client want to know financial information on top of progress information. But what we talk about in this thread is "% of Progress for total project"



I am not ignoring the importance of $. But how to express progress in its best form. Awaiting your input and demonstration of express progress in $ spend.



if I offend anyone, I apologise, however, my concern is "planner"IMHO (In my humble opinion) should be the one who know the importance of correct representation of true physical progress and reflected in the best possible way. We are not QS or accountant, time and progress should be in our heart.



I had said enough, hopefully we can stop for a while and look at the big picture of what is the best way to representing physical progress.



Any comments are welcom



Alex

R
Rolyn Jalea 👤 Member for 22 years

Hi Edgar,



Bro, please try to use words which can’t hurt your fellow planners, what I’ve seen is that your becoming hostile my friend... We are here to try help each other out. They just try to reply on this thread based on their knowledge, experience & opinion regarding the questions asked, and in any way could help those planners who need it. I believe there’s no need to start questions just trying to outsmart others. I like this website bro, and those people behind this site had helped me once when I encountered a serious problem regarding my programme.

With regards to your reply, IMO graphical presentation, together with tabular report on how you get the progress is still the best tool while presenting your progress to the Client... and right now, our client is paying us our interim monthy valuation based on that.

For the contract, there are 3 selections on how to get a contract:

1) By client nomination (which you have said by trust)

2) By becoming the lowest bidder

3) If the bid price don’t have a big margin with respect to bidders, most of the time, client choose the contractor with the best background and good reputation with regards to that field.



PEACE!!!!!



Rolyn

R
Raja Izat Raja Ibrahim 👤 Member for 21 years

Hi Alex,

I try to explain the best I could, what I mean,

1.Client very particular about claims that come from contractors. Their worry is to made payment more then progress at site(as per report not as per actual at site). Basically they already plan their payment schedule (by monthly or by milestone).

2.Client very worried if they already paid their contractor as per schedule, but the contractor cannot deliver their commitment to project like supply tools / equipment, labour etc on time. Somtimes worker strike cause not being paid or late payment by their contractor. This will make project delay and cause more money to find new labour or another contractor before client can back charge the contractor.

I hope this will do......

A
Alex Wong 👤 Member for 23 years 3 months

Raja



""

Hi Alex, this is my opinion, evrybody can make their opinion isnt it? on matter right or wrong, what i think is...""



Please dont take it personal, I only state my though as well please share your view of reporting progress in $ terms. Very interest to see how. Especially how to compare with plan expenditure without disclosing actual expenditure (Contractor not client).





"2. Believe me or not Client did care about dollar and cents, a) They aware on evry claim being submit, what they afraid is overclaim "



Are we talk about reporting progress - yes they do need financial report. To reporting progress??



"and the status is not as per progress they claim. It will burst their budget as per their plan to be."



How to calculate their (Please clarify who’s budget) budget variance without actuals - is that mean you have to disclose your actuals or their actuals. If it is their actuals (the client) so how they can predict are you (the contractor) going to burst or not??



"b) they care about their contrators from losing control their budget, may cause bankruptcy or burst their budget, its make more difficult to control the project."



Is the client control your project budget or U (The project management team), or the client control their budget?



Reporting progress is reporting contractor progress information - information that the client dont have.



Alex

A
Alex Wong 👤 Member for 23 years 3 months

Raja

I am only express my opinion, may be my english is no good at all because I dont understand a word you said in your last post and also can you please explain what you mean by "dollar & cents to report progress"

Alex

A
Alex Wong 👤 Member for 23 years 3 months

Dear All,



It is an interesting concept of disclosing internal financial information to the client. In my project management life, it is very rare to do such thing as regular progress reporting except "cost plus" type projects.

IMHO it is rare because

1. Client cannot verify your $ report and statement - I think they are not allow to see your accounting system plus all the invoices. If they are the one managing the cost why do they need you (Contractor). And if you disclose this information your margin is exposed to the client.



2. Even they can verify the reports; I think in most contracts, the project manager is responsible for managing budget, cash flow, procurement, risk... It is not the client to bare that risk and responsibility. As I said unless it is a cost plus project, I don’t see a reason why report regularly on cost you spend.



The only occasion I regularly reporting the financial situation is because the project is in real trouble.

As a joint solution, one of the activities is subsidised by the client and the financial reporting of that particular activity is report regularly to the client.

Cheers

Alex

E
Edgar Ariete 👤 Member for 20 years 10 months

Hi to All,



I had too much of your esperanto(s), but thanks anyway.



We can get all the information we need from this infobahn. My question is how can you make planning the simpliest you can?...for any Client who doesn’t know anything about intellegent machines to understand. Pictures? Will the client pay you by just showing him pictures? Figures maybe,

but how? Show him graphics blah blah blah, we’re living in a real world...Remember, you got the contract because of TRUST.



Thanks

R
Raja Izat Raja Ibrahim 👤 Member for 21 years

Hi Alex, this is my opinion, evrybody can make their opinion isnt it? on matter right or wrong, what i think is...

1. the project team more prefer no document at all, they didnt like burden with paper, they more intrested in construct and execution, with or without planner they still can manage the project, maybe cause bad experience having a planner which doing history reporting but thanks to contract and auditor make planner very valuable as reporter and compiler.(But not all...some planner)I believe most of planner in PP can drive the project.

2. Believe me or not Client did care about dollar and cents, a) They aware on evry claim being submit, what they afraid is overclaim and the status is not as per progress they claim.It will burst their budget as per their plan to be. b) they care about their contrators from losing control their budget, may cause bankruptcy or burst their budget, its make more difficult to control the project.

There is more we can discuss....but step by step we try to discuss.

A
Alex Wong 👤 Member for 23 years 3 months

Hi there,



1. Different from Software and manual planning

* Reuseability - In paper you have to draw the logic each time you change it. In a software you just update it as it go

* Calculation power, you can draw a 100 activity network using pen and paper, but you cannot do it when it is 10000 or 50,000 activity.

*Accuracy - Human are bound to have errors





2. Picture - client is not interest how much you spend rather how much you built. A picture can tell a thousand words.

3. Earn Value with Weighted factor

4. CLK Airport Projects - 3 contracts



HTH



Alex

R
Raja Izat Raja Ibrahim 👤 Member for 21 years

HI Edgar,

well this is my answer.

1. the diffrent is Paper and ink.

2. Using Dollar and cents.

3. Using how many numbers.

4. Anywhere.

V
Vladimir Liberzon 👤 Member for 25 years 4 months

1. No difference. The same logic. But you will not be able to produce manual calculations in the reasonable time.

2. We usually start with the teaching of our clients.

3. We use physical units of measure like meters, tons, cubic meters, etc.

4. We use physical measures in all projects.

Best Regards.

E
Edgar Ariete 👤 Member for 20 years 10 months



Hi there,



How are u Vishwas B? I have some questions for the big Planners out there (If I may).



1. What’s the difference between the conventional (manual)planning & the most highly sophisticated planning (using blah blah blah softwares) in terms of principles without considering the speed of the preparation?



2. How do you present, or how do you convince a client who doesn’t know anything about computers (but with a billion dollar on his account) with your computer generated reports?



3. What’s the most accurate unit of measure you use in your planning in terms of practicality?



4. Which project did you use it?

V
Vishwas Bindiganavale 👤 Member for 22 years 1 month

Hi Planners,



Thanks very much for your feed-back. My original post was a question in ’Lateral Thought’ and not to be applied in practise.



Happy Planning



Vishwas

C
Charleston-Joseph Orbe 👤 Member for 20 years 10 months

Hi Vishwas



The percentage arrive in your original query does not represent "overall physical progress". The physical progress of an activity is the quantities installed divided by the extimated total quantities.



But then you have 4,000 activities with different percent progress as the construction project goes on. You need to find a common denominator that relates to physical progress to get the equivalent percentage of each activities.



The question is what is the common denominator that relates nearly to physical progress. We planners know this. Am I correct? ??



Cheers,



Charlie

R
Raja Izat Raja Ibrahim 👤 Member for 21 years

as your request, simple sample....using duration

Description Wtg Dur

Project (XXX-XXXX)

1 Activites 1 ---- 7.78 ---- 7

2 Activites 2 ---- 11.11 ---- 10

3 Activites 3 ---- 11.11 ---- 10

4 Activites 4 ---- 22.22 ---- 20

5 Activites 5 ---- 22.22 ---- 20

6 Activites 6 ---- 5.56 ---- 5

7 Activites 7 ---- 5.56 ---- 5

8 Activites 8 ---- 7.78 ---- 7

9 Activites 9 ---- 3.33 ---- 3

10 Activites 10 ---- 3.33 ---- 3

Total ---- 100 ---- 90

S
Sriram Iyer 👤 Member for 22 years 7 months

Hello,

It is very simple.



Activity a = Total qty = Convert qty into Manhours using productivity - Hrs for the activity



Activity b = Total qty = Convert qty into Manhours using productivity - Hrs for the activity



Workout the total hrs = u can get the weightage of the individual activities & total activities.

P
Philip Jonker 👤 Member for 21 years 7 months

Hi Vishwas,



Bernardt is right, add resources in manhours and export to a spreadsheet in excel and calculate the percentages there. It is simple and accurate. However, I do not see the the reason for two decimals, maybe there is room for one, but the room for error is rather great as progress is a rather subjective matter, and as such not very scientific, and as percentage is already a two decimal issue, why try for four in the case of an inaccurate/subjective science? The same thing applies to costing, where you work to the nearest thousand.



I have people reporting to me on a weekly basis, using two decimals, and I do not believe a word of it.



Regards



Philip


E
Edgar Ariete 👤 Member for 20 years 10 months



Hi,



I suggest you calculate it manually everytime you update progress just to make sure (don’t use any machine). Yes, Raja is right.



Or you can try another formula with lesser zeros...so that if your progress will result to negative(-), you won’t be surprised...



Keep on planning anyway...

R
Raja Izat Raja Ibrahim 👤 Member for 21 years

if i not mistaken, u are counting activities, the activities is not showing u are ahead or behind, Its showing how many activities is complete. To show u very productive u have to measure overall duration = 100% because not every activities have same durtaion.

S
Steven Oliver 👤 Member for 23 years 7 months

In the absence of any other measure, I have previously used the ratio of the sum of remaining duration/sumof original durations.




S
Shahzad Munawar 👤 Member for 22 years 11 months

% age Progress in round figure is acceptable to each Client so two decimal or four does not matter.



Further Manhours is best yardstick to measure progress.

Z
Zhang Haixiang 👤 Member for 21 years 1 month

Hi,



the way u use is just counting activities.

the best way is to load manhours,if you are not going to do this,try to use duration (as Steven and Sukumaran mentioned)

S
Se de Leon 👤 Member for 25 years

Hi Vishwas,



For me there’s no specific answer to your question. It will really depend on your appreciation on how to use %Progress of your project.



In your case, each activity is equal regardless of how long or how hard you will do an activity. It does not represent the effort to do each activity. Using resources and duration(if duration calculation is correct not a guess), you are weighing each activity based on how it will influenced your programme in terms of effort and scheduling. I don’t normally use cost when weighing progress. It could sometimes be very confusing.



I could use your formula if ever the nature of the project is as such. But i will never use it in construction projects where productivity rates are defined and how hard or how easy the effort to do activities is very obvious.



To me, % complete is only indicative. There’s no absolute correctness on this issue. The only absolute is if it is 0% and if it is 100% In between, it’s just an indication.



Cheers,

Se


S
Sen Moc 👤 Member for 20 years 9 months

Vishwas,



Actually, what you did was you have calculated progress by considering equal weights to each activity. Unless all of your activities have approximately equal weights, your progress calculation is acceptable otherwise it’s not correct & inaccurate.



Let me show you an example considering only three (3) activities, for simplicity:



Activity 1 (orig. duration = 1 day; 100% complete)

Activity 2 (orig. duration = 1 day; 100% complete)

Activity 3 (orig. duration = 10 days; 4 days remaining, thus 60% complete)



Vishwas Method:



Sum of all the Percentages = 1*100%+1*100%+1*100% = 300%

Sum of Achieved Activities = 1*100%+1*100%+1*60% = 260%

Percent Progress = 260/300 = 86.67%



“Weighted” Method:



Sum of all the Weight Factors (considering duration) = 1+1+10 = 12

Sum of Weighted Progress = 1*1.0+1*1.0+10*0.60 = 8.0

Percent Progress = 8/12 = 66.67%



Evidently, from the above presentation, Vishwas Method doesn’t provide an accurate status of the project.

A
Alex Wong 👤 Member for 23 years 3 months

Hi



Its all dependent on the amount of time you have and your client requirement.



Remember this, a schedule is not a precision machine. Not like a accountant looking @ his/her balance sheet. The accuracy is depending whether it will help your project manager to manage the project and your client to give a good judgement of the progress. Any methodology is better than no methodology. It is better to have some calculation than non. If you just do not have the resource and time to add all resource and update per activity per week. It is better to have some measurement than non.



HTH



Alex

S
Sukumaran Subaramaniyan 👤 Member for 21 years 3 months

Vishwas,



You can use duration as a dummy resources and assign to each activities. (i.e. resource = duration and units = day)



After update the percent complete column, export the infomation to excel or any database files to calculate the progress with 2 decimal points.



Regards.

G
Gwen Blair 👤 Member for 21 years 11 months

Got a Contract because of trust?



This is not the world I know, live in and work in.



Get real! You PROBABLY got the contract because you were the cheapest.


Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts