hello Steven & Noufel.
Thanx for your suggestions.
But Steven
pls explain what is meant by Load the activities with values rather than use a hammock.
Either
a) Load the activities with values, rather than use a hammock, or
b) Use two resources on the hammock, with seperate calenders, or
c) use two resources and offset the second to the end of the nonworking period.
HTH
Hello Moosa,
There is an indirect way to solve your problem. Make a new resource curve putting the percentages of usage at your way in the period divisions of the curve template. Then apply this curve to your resource for the hammock activity which will be something like Cashflow. I think your problem could be solved.
Happy Plaaning
Hai Steven Oliver,
I am using P3.
I cannot hammock both solid and hollow separately. Because Consultant wants both solid and hollow under block work title.
Not for this also;
some other works with same activities; but some have gap of 1 month with another and all connected through hammock, then how I can get the cash flow omitting the non work period?
Wilth out giving separate hammock there is any way?
Regrds
Depends what software you are using. Why not hammock both solid and hollow seperately ?.