Turnaround/Shutdown vs. EPC Project w/ Primavera
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
There are significant differences between turnarounds and EPC projects. Because the scope is only partially known when execution begins, turnarounds demand much stricter scope management controls. A constantly changing scope (and schedule) means that baseline schedules are useless measuring sticks for turnarounds. As the baseline schedule is the entire basis for measuring and tracking EPC project performance, it is clear that a different paradigm is required for turnarounds. A changing schedule (and manpower staffing requirements) make resource leveling, a popular tool for EPC projects, counter-productive for turnarounds. The compressed work basis for executing turnarounds means that all team members have less time to analyze and react to changing priorities. Problems that go unchecked can significantly impact the chances for a reaching the time and budget goals. As a consequence, there is a much greater need for using the schedule to drive the project execution in a turnaround (whereas it is sometimes used mostly as a contractual tool in EPC projects). It is critical for all schedule and progress information to be highly visible, timely, comprehensive and accurate.
- drawings
- specifications
- contracts
- permits, memos, etc.
- past turnaround experience
- inspection reports
- operations requests
- historical estimates
during execution.
inspections are made.
advance of the project.
until the scope is approved, generally near
the shutdown date.
codes / commodities.
to perform work.
permitting every shift.
do not change.
during execution due to scope fluctuations.
weekly or monthly.
every shift, daily.
and months.
shifts.
large percentage of work can be postponed
to a later window of opportunity if
necessary.
Schedule acceleration can be used to
correct slippages in the critical path.
There may be little or no opportunity to
correct the critical path by accelerating the
schedule.