Loss of Rebar productivity - Change in density per

K
Katalin Hovanyi 👤 Member for 23 years 2 months

Haliho,

One thing the increased quantity other the design change. Once I was in similar situation. Recalculated a lot of things for the more or less 2 times as much rebar, I got 1.5 times much resource requirement and lost nearly a month because the design institute didn’t change the anchor design and simple there wasn’t enough place to put the anchors in. So the calculation and the formulas one thing and the real life is another.

Regards

Katalin

J
John Herbert 👤 Member for 21 years 4 months

assuming you have already submitted rebar rates, I agree with zhang your adjustment should focus on the increased tonnage.

Z
Zhang Haixiang 👤 Member for 21 years 2 months

Hi Raj,



First, the productivity is a rate (x ton/man.hour). increasing the density may increase the difficulty of installation, that will cause the loss of productivity, but not so much



For typical beam/slab, the desity of rebar should be within a certain range specified by design code to ensure the strength of the structure and also easy to construct. I don’t think there will be a significant loss of productivity if the density is within a reasonable range.



I think the key problem is the quantity increased greatly (3 times), so you need more time or resources.



I suppose you focus on quantity rather than productivity

N
N.M.Raj Nadarajan 👤 Member for 21 years 9 months

Hi All,



Let me try to answer all your queries:



1. Firstly, we did not have any typical rebar details in the Contract; it was a provisional item. However, an indicative tonnage per cu.m was included in the BoQ to aid tenderers.



2. The actual density on site is almost 3 times more (Beams & slabs). As Alex wrote earlier, this has also resulted in an increase in complexity…ergo loss in productivity. I am aware that the density could increase by simply increasing the size of the rebar and that this would, in fact, result in improved productivity. However, my question is related to loss of productivity due increase in density ( and complexity) with no change in rebar diameters i.e. only the number of bars have been increased.



3. Now, the question is this…is there any literature/norms/studies which would help me to get an idea of the loss in productivity due to this increased density/complexity?



4. I cannot rely on site data as I don’t have anything to compare the on-site productivity to…!!



Thanks for your input guys…



Regards,



Raj

S
Sunil Kumar 👤 Member for 21 years 2 months

Hellow Raj,



As Alex say there would an increse in rebar which will increase the manpower requirement. Then increase in Rebar / rebar per person will give you total mandays required to do the job...



Trsut this should suffice



Sunil

A
Alex Wong 👤 Member for 23 years 4 months

Raj



Instead of man hours loss in productivity, how about man hours increase due to, increase complexity, increase number of rebars, more difficult to access and number of cycles increase.



Cheers



ALex

Z
Zhang Haixiang 👤 Member for 21 years 2 months

Hi,



could you first explain, why there is a loss of productivity when the desity of rebar increase.

Forum Sponsor

Top Posters

James Williams
74 posts
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts