Planning, Scheduling & Programming Discussion Member for 20 years 7 months Member for 20 years 7 months Submitted by Zhang Haixiang on Wed, 2005-06-29 01:22 Permalink RE: Contiguous piling outputs 1 pile(800 dia, 40m )/24 hr in very poor soil ,mud protected ( fill mud in the hole to protect it from collapse) Member for 20 years 4 months Member for 20 years 4 months Submitted by Hervé de Trogoff on Tue, 2005-06-28 13:29 Permalink RE: Contiguous piling outputs Thanks Bill for the insight information. I also spent a few years in the Guinean Golf and whats for sure is that down times of 30 % are not unusual there! I am awaiting soil investigations to refine estimate outputs. Hervé Log in or register to post comments
Member for 20 years 7 months Member for 20 years 7 months Submitted by Zhang Haixiang on Wed, 2005-06-29 01:22 Permalink RE: Contiguous piling outputs 1 pile(800 dia, 40m )/24 hr in very poor soil ,mud protected ( fill mud in the hole to protect it from collapse)
Member for 20 years 4 months Member for 20 years 4 months Submitted by Hervé de Trogoff on Tue, 2005-06-28 13:29 Permalink RE: Contiguous piling outputs Thanks Bill for the insight information. I also spent a few years in the Guinean Golf and whats for sure is that down times of 30 % are not unusual there! I am awaiting soil investigations to refine estimate outputs. Hervé
Member for
20 years 7 monthsRE: Contiguous piling outputs
1 pile(800 dia, 40m )/24 hr in very poor soil ,mud protected ( fill mud in the hole to protect it from collapse)
Member for
20 years 4 monthsRE: Contiguous piling outputs
Thanks Bill for the insight information. I also spent a few years in the Guinean Golf and whats for sure is that down times of 30 % are not unusual there!
I am awaiting soil investigations to refine estimate outputs.