Contiguous piling outputs

Z
Zhang Haixiang 👤 Member for 21 years 2 months

1 pile(800 dia, 40m )/24 hr in very poor soil ,mud protected ( fill mud in the hole to protect it from collapse)

H
Hervé de Trogoff 👤 Member for 21 years

Thanks Bill for the insight information. I also spent a few years in the Guinean Golf and what’s for sure is that down times of 30 % are not unusual there!



I am awaiting soil investigations to refine estimate outputs.



Hervé