The resource pool has permissions set to it now. full control to planners and have removed the everyone group so when someone else other than a planner saves a project it cannot link back to the resource pool and thus wreck everything.
60 ish projects yes but there arent that many changes and none of them that large (Petro/Chem ind)and could be just changing a pipe etc. This role isnt an in depth planning role so no business need for p3 other than it can do more.
saving as a web page; when doing this it asks for a report, PMs like to see it as MS proj layout (whole thing), I think PDF format may cause a lot of work as youd need to save every possible view??
P3 would be a god send sadly no available here Ive tried
After you have completed the Update you save your work normal and then you go Save as (And make use of the TEXT / WEB Page etc Reports) Depended on what the PM needs to see. BUT I Would suggest you Get Acrobat Writer. (You dont even need to open up the Project to print you select them all in Explore Create a combined PDF walk away come back after lunch. AND IT IS DONE. No Time Wasted. Normally companys (Especialy IT Companys) Have Acrobat Writer to send Design/Layout/etc to client to view.
I would suggest have a look in the company they should have a spare licence on a computer that you should be able to use once a week.
I had this a while back (wsa MSP 200), the normal sales talk, that MSP allowed this over the net, ie each resources was allowed to update his own portion of the project, however, I wasn’t able to apply the theory as I could never get any definitive answers from MS, as their so-called experts who we hired at a ridiculous rate, could not answer the most basic question, Jaco and Bill might have a grasp of this, the expert charged ZAR 650 an hour, and took notes of all the questions and was going to come back with replies, which never happened.
If you have to handle 60 projects, the cost of P3 should not be a problem, and then it is easy, make each resource a sub-project, and set the access rights. You can use suretrack, for the resources to access and update their portions. If you know what you are doing, you can create database files for each resource and these can be updated in excel or Access and then be imported. There is a hundred ways to skin a cat.
I guess not a bad idea if you have adobe on your PC but my project managers need to see the plans and there are so many of them it would be too much work. Since there updated weekly i just cant do it (60+ projects)
Why does the resources need to view the Plan. I have a rule nobody access my schedule. I will issue it to them. A simple solution is to PDF the reports. And dont give anybody access. This mean you need to once a day/week/month PDF the report and email/Newtork it.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
just for info i managed to sort out my problem
The resource pool has permissions set to it now. full control to planners and have removed the everyone group so when someone else other than a planner saves a project it cannot link back to the resource pool and thus wreck everything.
Guys thanks again
60 ish projects yes but there arent that many changes and none of them that large (Petro/Chem ind)and could be just changing a pipe etc. This role isnt an in depth planning role so no business need for p3 other than it can do more.
saving as a web page; when doing this it asks for a report, PMs like to see it as MS proj layout (whole thing), I think PDF format may cause a lot of work as youd need to save every possible view??
P3 would be a god send sadly no available here Ive tried
Hi John
Another Option (Since it is 60 Project a week)
After you have completed the Update you save your work normal and then you go Save as (And make use of the TEXT / WEB Page etc Reports) Depended on what the PM needs to see. BUT I Would suggest you Get Acrobat Writer. (You dont even need to open up the Project to print you select them all in Explore Create a combined PDF walk away come back after lunch. AND IT IS DONE. No Time Wasted. Normally companys (Especialy IT Companys) Have Acrobat Writer to send Design/Layout/etc to client to view.
I would suggest have a look in the company they should have a spare licence on a computer that you should be able to use once a week.
Cheers
Best of Luck
Hi Guys,
I had this a while back (wsa MSP 200), the normal sales talk, that MSP allowed this over the net, ie each resources was allowed to update his own portion of the project, however, I wasn’t able to apply the theory as I could never get any definitive answers from MS, as their so-called experts who we hired at a ridiculous rate, could not answer the most basic question, Jaco and Bill might have a grasp of this, the expert charged ZAR 650 an hour, and took notes of all the questions and was going to come back with replies, which never happened.
If you have to handle 60 projects, the cost of P3 should not be a problem, and then it is easy, make each resource a sub-project, and set the access rights. You can use suretrack, for the resources to access and update their portions. If you know what you are doing, you can create database files for each resource and these can be updated in excel or Access and then be imported. There is a hundred ways to skin a cat.
Hope this is of assistance.
Regards
Philip
I guess not a bad idea if you have adobe on your PC but my project managers need to see the plans and there are so many of them it would be too much work. Since there updated weekly i just cant do it (60+ projects)
Hi John
Why does the resources need to view the Plan. I have a rule nobody access my schedule. I will issue it to them. A simple solution is to PDF the reports. And dont give anybody access. This mean you need to once a day/week/month PDF the report and email/Newtork it.