Project Planning & Scheduling

Manager of Project Controls, Foster Wheeler Constructors, Inc, (various projects)

START Date
END Date
Experience Hours (Planning & Scheduling)
17000
Experience Hours (Cost Management)
10000
Experience Hours (Forensic Analysis)
2000

As a Project Controls Manager, I was responsible for overall Project Control for the Home Office & job sites on assigned projects.  Projects included the construction of a Silicon Polyreaction facility in Butte, MT., and Resource Recovery Facilities in Camden NJ, Hudson Falls, NY and Robbins, IL. Petrochemical expansions for Ashland Oil in Cattlesburgh KY, Fina Oil in Port Arthur TX, Maraven in Cardon, Venezuela, and Uno-Ven in Lemont IL.  Cost Control is provided using J.D.

Senior Engineer - Planning, Associated Constructions & Investments LLC, Jumeirah Lake Tower - Retail Development

START Date
END Date

Leads planning, scheduling, cost control for all phases of the projects



• Participates in project planning processes, define scopes, establishing WBS & budgets on allocated projects



• Responsible for developing and maintaining project schedules on Prim

PLANNING ENGINEER, ENERMES ENGINEERING QATAR W.L.L., Pearl Qatar (2B+G+21+R)-MEP Installation, VB 20 & 21

START Date
END Date
Experience Hours (Planning & Scheduling)
2000
Experience Hours (Cost Management)
300
  • Prepare & update base line Schedule & Update the schedule weekly basis.
  • Identify the critical activities closely monitor to avoid the delay on the project.
  • Closely monitor the procurement of the material to maintain the baseline without any impact.
  • Issue the weekly target on the floor layout to the project team
  • Prepare weekly and monthly progress reports to main contractor.
  • Attend progress meetings with main contractor and engineers.
  • Issue 2weeks look ahead to site team to identify the forecast activities to align the baseline tar