EPC Senior Planner, Larsen & Toubro - ECC, Bangalore Metro Rail Project

START Date
END Date

1.      Overall responsibility of Planning – Viaduct in co-ordination with the Stations team

2.      Schedule preparation, monitoring progress and updating schedule (Initial schedule with MSP and subsequently working on P6 package).

3.      CPM Programme for Viaduct Project.

4.      Updating the Baseline Programme & Recovery Programmes.

Lead Project Planner EPCM, Fluor, New Synfuels Reactor Projects

START Date
END Date
Experience Hours (Planning & Scheduling)
2500
Experience Hours (Forensic Analysis)
500

Project Lead Planner responsible for developing, implimenting and maintaining project schedules and progress reporting and control systems.

Senior planning engineer, M+W Group, Industrial

START Date
END Date

 

 

Ø  Site Start Up and Creation of Necessary Documents.

Ø  Making of L1, L2 and L3 Schedule.

Ø  Planning of the Project with respect to Mile stone and Priority

Ø  Derivation of Package wise Weightage and Progress Curve Projections

Ø  Coordination with Design Consultant, contractor and Client

Senior planning engineer, M+W Group, Industrial

START Date
END Date

 

 

Ø  Site Start Up and Creation of Necessary Documents.

Ø  Making of L1, L2 and L3 Schedule.

Ø  Planning of the Project with respect to Mile stone and Priority

Ø  Derivation of Package wise Weightage and Progress Curve Projections

Ø  Coordination with Design Consultant, contractor and Client

Construction management: , SOGEFINSA, Multi-use stadium in Granada, Spain. 22.524 spectators

START Date
END Date

Specialist Planner. Target plan and weekly control. Prefabricated Precast Concrete multi-use stadium.

Construction management: Project Planning, Bid Analysis, Scheduling, time-cost control and reporting. 

Project Director, IPECC Consultants, SHELL PAKISTAN LIMITED - Safety & Security Project at LOBP Keamari

S
Shuja Ali 👤 Member for 15 years 11 months
START Date
END Date

 

SHELL PAKISTAN LIMITED - Safety & Security Project at LOBP Keamari

  • April 2011 to September 2011

Supply, Installation & Commissioning of Safety & Security Items at Main Gate of LOBP Keamari