Manager - Project Controls, ESSAR Construction Overseas LTD, Refinary - Carbon block delayed coker unit costruction

START Date
Experience Hours (Planning & Scheduling)
4000
Experience Hours (Cost Management)
17000
Experience Hours (Forensic Analysis)
900

Ø  Planning, Resource requirement, cash flow statements, fund requirement and Co-ordination with all department for smooth execution.

Ø  Monitoring the project activities on daily basis and identify the critical activities and give the information to execution team to achieve target within the agreed time. If fails, for Recovery plan discussion with field engineers. Co-ordination with Head of office and make the strong coordination between client and field engineers.

Senior planning Engineer, Ed Zublin AG, SHIEK ZAYED DESERT LEARNING CENTRE & UAE WORLD DESERT, NON-PROCESS PACKAGE OF RUWAIS REFINERY EXPANSION PROJECT

START Date
END Date
Experience Hours (Planning & Scheduling)
8000
Experience Hours (Cost Management)
1000
Experience Hours (Forensic Analysis)
4000

Responsibilities:
1. Formulates recovery schedule to recover lost time.
2. Define and coordinate specific activities and work tasks.
3. Assign and allocate resources to competing activities.
4.

Project Control Manager, "J.A. Jones Construction Group, LLC", $450MM brewery expansion

START Date
END Date
Experience Hours (Planning & Scheduling)
2500
Experience Hours (Cost Management)
1500
Experience Hours (Forensic Analysis)
300

Responsible for establishing and supervising a Project Control Organization for a $450MM major modernization and expansion construciton project for Anheuser-Busch in Newark NJ.  This included bringing a new corporate cost system (McCosker) on line, establishing procedures and modifying systems to support project control.  This project was unique in that that the project was set up as a profit center, and the McCosker system was initiated on this project 18 months before the company changed over to the new system.  Project planning was accomplished using Artemis & Pri

Assistant Planning Engineer, Laing O'Rourke, Dubai University Hospital

START Date
END Date

Project: University Hospital, Dubai Health Care City.

 

Project consisting 3 Basements (circa 31,000 m2 each), 5-storey (circa 15,000 m2/floor) Podium housing clinics operation theaters, public areas, and 14-storey (circa 4,500 m2/floor) Hospital Tower building, in addition to a 7-storey Admin building (circa 2,100 m2/floor).

Project value: US $ 180 Million.

 

• Project control and management (program of work, S curve, Resources plans. etc.)

• Provide a full planning, work management and analysis of construction activities.

PLANNING ENGINEER, Foster Wheeler, Provision of Expert Technical Services

START Date
END Date
Experience Hours (Planning & Scheduling)
3050
Experience Hours (Cost Management)
1050

Planning engineer seconded to DUSUP through Ingen Ideas LLC (Now part of Foster wheeler) for a Gas plant expansion project. Responsibilities include:

       -Project Planning , Progress reporting

      - Integrating/ tracking contractor plans into Master schedule

     - tracking contract variations

      - Input to weekly/ monthly reports

      - Developement and mainteneance of Doc Control system

Planning Engineer, Sepam Qatar, NDIA- New Doha International Airport- Terminal Complex Lounges

START Date
Experience Hours (Planning & Scheduling)
4700
Experience Hours (Cost Management)
2650
Experience Hours (Forensic Analysis)
1300

Ø   Responsibleforplanning,reviewandoversightofconstructionprojectmaterialscontrols,documentcontrols. ResponsibleforPlanningandSchedulingforNDIAloungefitout project.

Ø   InterfacewithProjectManager,ConstructionManager,ConstructionCoordinators,Planning&Controls,Engineeringandlogisticalpersonnel.

Ø   SubmitstoclientandtoSEPAMmanagementaccurateandontimereportsonprojectplanning&scheduling&progress variances.

Planning Engineer, Sepam Qatar, NDIA- New Doha International Airport- Terminal Complex Lounges

START Date
Experience Hours (Planning & Scheduling)
5000
Experience Hours (Cost Management)
2650
Experience Hours (Forensic Analysis)
1300

Ø   Responsibleforplanning,reviewandoversightofconstructionprojectmaterialscontrols,documentcontrols. ResponsibleforPlanningandSchedulingforNDIAloungefitout project.

Ø   InterfacewithProjectManager,ConstructionManager,ConstructionCoordinators,Planning&Controls,Engineeringandlogisticalpersonnel.

Ø   SubmitstoclientandtoSEPAMmanagementaccurateandontimereportsonprojectplanning&scheduling&progress variances.

Senior Planner- , Trocon International , University of Baghdad , Halls of Residence and Dinning Halls

START Date
END Date
Experience Hours (Planning & Scheduling)
2900
Experience Hours (Cost Management)
200
Experience Hours (Forensic Analysis)
0

 

 

Site project planner on the construction of the Halls of Residence for the University of Bagdad