)Planning

Senior Planner / Scheduler, Dar Al Handasah (Shair & Partners), JUMEIRAH VILLAGE

S
sreejesh kc 👤 Member for 22 years 1 month
START Date
  • Established a planning system and led a team of three planners to manage a USD 425 million project, which comprised of 1573 villas and townhouses covering 375,000 m2 built up area with peak manpower of 5000 labours.
  • Examined, recommended, advised, consented and handled the contractor’s master programmes with 40,000 activities in a single project.
  • Strengthened company procedures and MIS reporting templates to match exact project requirements and significantly improved the coordination and communication between all stakeholders.

CONSTRUCTION/PLANNING ENGINEER, BRUNSFIELD GROUP OF COMPANIES MALAYSIA, OASIS SQUARE ARA DAMANSARA

K
kalaivanan 👤 Member for 15 years 9 months
START Date

 

  • Monitoring information and feed back necessary for the progress development of the Master Implementation Programme.
  • Establishment of work programmes for an effective Project Planning and Monitoring of the progress of works on site within the frame work of the Master Implementation Programme.
  • Periodic updating of the Master Implementation Programme, works programme and all other related programmes.
  • Provide technical planning support for Site Project manager in planning related matters.

Senior Project Planner, Dockwise, Various Heavy Transport, Float Over, Engineering Projects

START Date
  • Assist with the selection of new personnel
  • Introducing and implementing new Project Risk Management System
  • Control/lead of Project risk analyses
  • Training of new Project Planners
  • SAP – PS implementation
  • Member of the SAP-Control team
  • Steering and coaching of other Project planners
  • Introducing “Project Planning” as a process within the company.
  • Set-up of planning department
  • Creating of procedures and plans
  • Create proposal & project schedules
  • Follow-up, analyze and control o

Planning Manager, Churngold Construction Limited, Various - Civil Engineering & Building

START Date
END Date

 

Planning manger in Building Industry with specialist earth and ground works contractor. responsible for tender and construction phase planning. Claims and demonstartion of delay & disruption, prolongation and formal EOT to various forms of contract.

Sideline role in Quality and Environmental Sytems bringing ISO 9001 and 14001 to the business and over seeing its implementation and upkeep.

Quasi Contracts Manager role covering site and specific skilled teams including CCTV and Drainage jetting.

Planning Engineer, Afcons Infrastructure Limited, A variety of tenders and site based projects

START Date
END Date

- Preparation of Contract Appreciation Document

- Preparation of Tender Programs
- Preparation of General and Detailed Method Statement
- Preparation of Construction Schedule Using Primavera
- Preparation of Accelerated Program & Catch up Plan
- Preparation of Extension of Time Program
- Preparation of Cash Flow Curves
- Preparation of Resource Allocation & Leveling
- Preparation of Planned Vs Actual Progress Program
- Preparation of Impact Program

- Cost & Claims Analysis

- Subcontractor Planning

- Preparation of Procureme

Senior Planner engineer, Vinci Contruction Grands Projets, Lusail LRT

START Date
END Date

 

Construction of the time schedule of Lusail Railway Transit System:

 

  • Establishment of the Work Breakdown Structure (WBS=GBSxPBSxABS);
  • Creation of the time schedule of the project (3000 tasks), Gantt & trip diagrams, in the time allowed (40 days).