)Planning

Planning & cost manager, SYSTRA, Project management departement

START Date
END Date

Main activities:

  • Development of methods and tools about planning, risks, cost estimation & cost control
  • Development of a new approach for project structuration: 3D WBS
  • Creation of a standard database of all the planning tasks (PBS, ABS) to be deployed on projects
  • Planning of differents LRT projects
  • Daily use of MS PROJECT, PRIMAVERA P6 and TILOS 6
  • EXCEL and ACCESS VBA programming, also in VB.NET.

Senior Planning Engineer - Construction, AMANA CONTRACTING & STEEL BUILDINGS, Head Office Planning Management

S
sameh sliem 👤 Member for 15 years 10 months
START Date
END Date
  • PMP certified
  • Prepare and present detailed planning information (Gantt charts, histograms, Bar charts, WBS, Baseline Schedules & S Curves) for projects and commercial tenders.
  • Develop all planning and scheduling tools to be used in control, monitoring and reporting of projects status.
  • Anal

Asst Development & maintenance Engineer, SPEL GROUP, Development of mold for KFC rice bowl

START Date
END Date

 

 Development of new products Planning & Scheduling of assigned projects using Primavera Generation, issuance & follow up of Preventive Maintenance Monthly & Quarterly Plans. Follow up of preventive & plannedmaintenance to avoid any unforeseen breakdown of Plant equipment. Preparation, update & review of Job Plans, Work instructions & Procedures.

Planning Manager, Six construct - (Besix), Construction of ADNOC New Corporate Headquarters

START Date

- Six Construct was awarded the construction of The Abu Dhabi National Oil Company Headquarters, which has been designed to become a landmark and the highest tower in the UAE capital.

The main duties achieved during the short period of assignment are;

1.

Planning/Scheduling Assistant, Sunway Construction (Caribbean) Ltd, High rise Buildings

START Date
END Date

 

Safiyyah Khan has approximately 5 years of experience in the planning and scheduling field but it’s more in the capacity of assisting project managers, planning managers and cost engineers.

Site based construction planner, Tracey Brunstrom & Hammond, Colongra Peak Power Gas Turbine

START Date
END Date

The majority of Andrew’s work has included:

 

  • Strategic Programme Planning and Programme Critical Path Analysis

 

Experience in the preparation of program analysis of scope and dependencies mapping, to identify critical path for complex programs of works

 

  • Programming, Time Control and EOT Analysis

 

Experience in the p

Planner, LIZ, Highways

START Date

Will be responsible for project Planning, co-ordination and reporting activities related to the project.

 

Job Summary:

Shall focus on the following Perspective of the business i.e.

1. Project Scheduling

2. Project Reporting

3. Co-ordinating with Client and   Office


4. Assistance to Site Manager

 

Broad Responsibilities / Major Deliverables:

1. Project Scheduling Activities

a. Update and Monitor the existing Project Schedule.

b.