EPC Lead Planner, James Fisher Nuclear Limited, SGHWR
Lead Planner - James Fisher Nuclear Ltd
- Took the lead for a number of programmes related to the delivery of a project to deconstruct one of the legacy R&D Reactors for Magnox
- Developed, with information I collated, a detailed construction programme that included a complicated Mechanical and Electrical installation phase.
- Rebaselined the contract programme with the civils and M&E installation sequence including the dependencies of the Safety Case Logic required ahead of major construction.
- Instigated a tracking system for the remaining design deli