Senior Planning Engineer, Larsen & Toubro (L & T) Limited, SADARA Poly Ethylene

S
Sagar Raut 👤 Member for 11 years 11 months
START Date
END Date
Experience Hours (Planning & Scheduling)
4500
Experience Hours (Cost Management)
4000
Experience Hours (Forensic Analysis)
3500

 

·            Creating & Maintaining a Schedule model to reflect realistic progress of the Project

·            Developed Primavera Schedule with resource (Labor & Material) loading, leveling to calculate manpower & material requirement in time phase in concern with Engineering, Procurement and Construction Team

Sr. Planning Engineer Based at HO, Rezayat Company Limited, •Construction of Primary and Secondary infrastructure in SABIC Housing Project in Haii Al-Mutrafiah – Jubail.

START Date
END Date

·         Establishing a schedule development process to develop a project schedule that includes the entire project scope of work, client requirements, schedule hierarchy, division of responsibility, schedule review, approval requirements, and distribution.

·         Developing a master project schedule, identifying major milestones to achieve the project completion date.