Kazakhstan (AS.KZ)

KZ

Planning & Controls Lead Engineer, GAMA-TEKFEN, Kashagan Field Development Experimental Programme - KMW Onshore Main Construction Works & Kashagan Tranche 3 Power Generation Plant EPC Contract

START Date
END Date
  • Preparation of  EPC and Construction Schedules (Total Direct Man-hours = 15.500.000)
  • Preparation of  Progress Measurement Systems and Integration with Other Departments
  • Preparation of Project Controls Procedures
  • Preparation of  Payment Certificate (for Kashagan Tranche 3 Power Generation Plant EPC Contract)
  • Personnel Time Recording Database Setup and Management
  • Updating and Forecasting Works with consolidated EPC Schedules.
  • Monitoring Variations over Scope of Work
  • Preparation of Daily, Weekly and Mon
Permanent Employment Kazakhstan (AS.KZ) $180k - $200k USD + Expat Package

PLANNING ENGINEER, Bonatti S.p.A, Electrical & Instrumentation and commissioning for onshore oil and gas

START Date
END Date

 

·         Daily monitoring the progress on Oil, Gas, Sulphur and Main Pipe rack Areas

·         Preparing the Daily, Weekly and Monthly progress reportsfor Management

·         Monitor the planning and progress procedures to ensure, that each element of the project performs the processes timely and consistently

Tamas Farkas

First Name
Tamas
Last Name
Farkas
Oldest experience
Years Experience
13
Telephone Number
+36 (20) 525-1725 (Hungary); +7 (701) 238-9848 (Kazakhstan)

Date of birth: 05th of October, 1970

Citizenship: Hungarian

E-mail: [email protected]

Skype: arteomo

Education:

GATE-GTK Karoly Robert College, Faculty of Economics, Gyongyos, Hungary – Economic Engineer (BSc course), 1994

Senior Planning engineer, PMC , EPC, Refinery, Pipeline, Greenfield & Brown field,

START Date
END Date

 

  • From March 05, 2011 to till Date – Senior Planning Engineer

Employer Name: PMC Services

Client Name : Takreer (Abu Dhabi Oil Refining Company)

Project Name: PMC services to RRE (Ruwis Refinery Expansion) Project

Location: Abu Dhabi, United Arab Emirates (UAE)

Summary: Refinery Expansion Project for CDU, RFCC, Utility, Offsite and other associates. Assigned with core group to control and monitor for all EPC no.

Planning Engineer, Agip KCO , Kashagan Project

START Date
END Date

Analyzed and ensured that all required project documents and engineering deliverables are set up to establish a proper project baseline, and monitored progress against those to the critical path. Responsible for the following projects: EPC 166MW Power Generation Plant, EPC Power Plant Utilities, C Main Pipe Rack Erection approx. 16500 tons of steel structures in total, EC 200 man Temporary Offices and four 1000 m2 each Warehouses.