M/s. Ankur Developers, Kolhapur Planner

Planning and scheduling to support the execution team in achieving milestones and completion dates.

Ensuring integration of the engineering, procurement and construction planning.

Development of Level 3 schedule using Primavera software detailing all items per discipline, with a budgeted labour value for each activity.

Weekly updating of earned man-hours for determining weighted progress per discipline and overall construction status.

Preparation of three months look-ahead schedule at Level 4 as a basis for monitoring actual execution.

M/s. Sai Samarth Associates, Pune Planner

Development of a detailed integrated baseline plan and schedule. Continuous updating and rigorous monitoring of schedule performance.

Monitoring the work progress and the costs incurred, compares those to the initial Baseline Budget and Schedule, and provides management with progress & performance reports (including Earned Value Reports).

Analyze Critical Paths and cost deviations and discuss the causes of deviations, impact of deviations, and corrective actions required.

Perform cost estimating, analysis, and control activities, as directed.

Executive Engineer- Mechanical, Kitex Garments Ltd., Construction of Textile Processing Plant and Associated Buildings, WTP plant

START Date
END Date

     Supervising the erection of equipments, pipes, steel structure and MEP works in factory and buildings.

     Planning for execution

     Organizing the resources required for execution (man power, contractors, materials and machinery)

     Implementation of execution plan by co-ordination meetings with contractors.

     Checking and certifying the bills, reconciliation and payment advices.